Work on the first phase of the Warwick Road route enhancements (from Percy Road to Stockfield Road) is due to start on Monday 6th December and is likely to last for ten weeks.
The work consists of:
To save time and waste, the work (carried out by Parade Civil Engineering Ltd) will be co-ordinated with the resurfacing of the Warwick Road under the Highways Maintenance contract with Amey, which is also due to be done between December and February.